Reconstruction of housing for the residents of the “Dobrorad” condominium association

Renovation

Reconstruction of housing for the residents of the “Dobrorad” condominium association

Project goal: Reconstruction of residents’ apartments following Russian missile strikes in 2022
  • Project area:
    678 m²
  • Number of beneficiaries:
    50
  • Project partner:
    “yeVidnovlennia”
  • Solidarity budget (planned):
    3.5 million
  • Solidarity budget (actual):
    2.97 million*
  • Project end date:
    August 2025

*The actual cost was lower than anticipated thanks to efficient financial management, favorable terms from suppliers, and logistical support from a strategic partner.

  • Project area:
    678 m²
  • Number of beneficiaries:
    50
  • Project partner:
    “yeVidnovlennia”
  • Solidarity budget (planned):
    3.5 million
  • Solidarity budget (actual):
    2.97 million*
  • Project end date:
    August 2025

*The actual cost was lower than anticipated thanks to efficient financial management, favorable terms from suppliers, and logistical support from a strategic partner.

Context and Challenge

The attack by the Russian Federation in 2022 caused significant destruction in many regions of Ukraine, including the Kyiv region. As a result, the “Dobrorad” condominium in the city of Irpin lost its roof due to direct impacts. Apartments on the upper floors (4th and 5th) were completely destroyed, the roof collapsed, and all belongings were burned. Fortunately, the residents were able to evacuate in time. After the liberation of the Kyiv region, upon returning home, they began looking for solutions to rebuild their housing. The priority was to restore the roof and load-bearing walls, as well as to fully renovate 16 apartments so that residents could move back in.

Before
After
Before
After
Solidarity’s Contribution

Our foundation provided everything necessary to first rebuild the roof and facade, and then the 16 apartments. We financed materials for all stages of the works—from rough construction to finishing and decorative works—so that residents could restore their homes: plaster, putty, paint, wallpaper, laminate flooring, doors, faucets, and much more. Thanks to this, residents were able to renovate their apartments much faster.

Project:
Apartment of the Adamliuk family
Before
After
Before
After
Project:
Apartment of the Bryk family
Before
After
Before
After
Project:
Apartment of the Volovodenko family
Before
After
Before
After
Project:
Apartment of the Kozovykh family
Before
After
Project:
Apartment of the Kosenko family
Before
After
Before
After
Project:
Apartment of the Lukianenko family
Before
After
Before
After
Project:
Apartment of the Mareechev family
Before
After
Before
After
Project:
Apartment of the Nastych family
Before
After
Before
After
Project:
Apartment of the Oliinyk family
Before
After
Before
After
Project:
Apartment of the Polovynka family
Before
After
Before
After
Project:
Apartment of the Roshchyn family
Before
After
Before
After
Project:
Apartment of the Sokolovskyi family
Before
After
Before
After
Project:
Apartment of the Sperkach family
Before
After
Before
After
Project:
Apartment of the Chebotariov family
Before
After
Before
After
Project:
Apartment of the Shuriakov family
Before
After
Before
After
Project:
Apartment of the Yartym family
Before
After
Before
After
Results and Impact

By August 2025, all apartments were ready for occupancy. Some residents had completed their renovations earlier, while others were still furnishing their homes, but the most important outcome is that the building has been restored and is now safe to live in. We helped residents preserve one of the most important things in their lives: their own home, a place where they can build their future.